Overview
Correct installation of the HYRIG 4" 5000psi Demco mud valve is essential to ensure safe, leak‑free operation and maximum service life. This guide provides all necessary dimensional data and a step‑by‑step installation procedure in full compliance with API 6A standards.
Valve Dimensions by Connection Type
| Connection | Height (mm) | Width (mm) | OEM Part Ref. |
|---|---|---|---|
| Threaded (NPT) | 630 | 330 | J007419 / M8419 |
| Butt-Weld (BW) | 630 | 330 | J007420 / M8420 |
| RTJ Flanged | 630 | 405 | J007421 / M8421 |
RTJ Flange Detailed Data
Flange O.D.: 292 mm
Bolt Quantity/Size: 8 bolts, 7/8" diameter
RTJ Ring: R-27
Bolt Circle: Standard API 6A dimensions
Butt‑Weld End Preparation
Schedule: XXH (Extra Extra Heavy)
Material: 4130 Alloy Steel compatible
Pre‑heat and post‑weld heat treatment (PWHT) required per API 6A
Prior to welding, the seat and bonnet seal must be removed from the valve body
Step‑by‑Step Installation Procedure
Step 1: Pre‑Installation Checks
Verify the valve size, pressure rating, and connection type match your piping.
Inspect all sealing surfaces for transit damage or contamination.
Ensure the valve is in the fully closed position before installation.
Step 2: Orientation & Clearance
Install with the flow arrow pointing downstream.
For rising stem valves, provide adequate vertical clearance for full stem travel.
Ensure the visual position window is accessible for inspection.
Step 3: Connection‑Specific Mounting
Butt‑Weld (BW) :
Remove seat and bonnet seals before welding.
Use XXH schedule pipe with 4130 compatible material.
Apply pre‑heat and perform post‑weld heat treatment (PWHT) per API 6A.
Allow cooling before reinstalling seals.
Threaded (NPT) :
Apply appropriate thread sealant compatible with service media.
Tighten to recommended torque values.
Do not over‑torque; avoid damage to threads.
RTJ Flanged :
Install RTJ ring (R‑27) in the groove.
Align flange bolt holes.
Install bolts (8 bolts, 7/8") and tighten in star pattern.
Torque to API 6A recommended values.
Hammer Union :
Align union halves.
Install O‑ring seal.
Tighten union nut with hammer wrench to API recommended torque.
Step 4: Post‑Installation Testing
Perform hydrostatic test per API 6A requirements.
Check all connections for leaks.
Cycle valve fully open and closed to verify smooth operation.
Step 5: Lubrication
Apply grease through grease fitting (STD-001).
Use grease compatible with service media and temperature.
Critical Installation Notes
Avoid collisions and damage to the valve during the installation process.
Ensure connections are firmly secured to the pipeline.
For sour service (H₂S), use NACE‑compliant materials and seals.
The visual position window should be kept clean for accurate reading.
For detailed torque charts or installation troubleshooting, contact info@hyrig.com.