XBSY Sand Pump Installation & Operation Guide

XBSY is the product brand shown in the sand pump manual; HYRIG can supply the XBSY sand pump range and spare parts. This guide summarizes the installation, operation and maintenance requirements from the manual.

Installation

  • Install the pump as near to the pumping source as possible to shorten the suction section and reduce suction loss.
  • Installation shall be horizontal, firm, reliable and vibration-prevention.
  • For motor direct drive, elastic shaft coupling alignment requires parallel offset no more than 0.25 mm and angular error no more than 0.12 mm.
  • For pulley drive, the two pulley axles shall be parallel with end error no more than 2 mm; the belt must be aligned and equally tensioned; the motor shall be balanced and locked.
  • Inlet pipeline section area must be larger than or equal to the pump section area.
  • Suction pipeline shall not be fitted with a throttle valve; a normally open valve may be used and closed only during inspection/repair.
  • To prevent bubbles, a gradual transition from high altitude to low altitude shall be provided between the pumping source and the pump.
  • The pipeline at the pump inlet must be horizontal and straight, with a length of at least twice the suction pipeline diameter.
  • When a hosepipe is used temporarily, ensure it is not compressed.
  • Outlet pipeline shall be fitted with a normally open valve for inspection/repair.
  • Each pipeline must have its own support. The pump must not bear pipeline weight.
  • When operating condition is unclear or unstable, the outlet pipeline must be equipped with a throttle valve.

Operation

Before startup:

  • Manually turn the pump shaft to ensure smooth operation without grating.
  • Fill the pump body and inlet pipeline with fluid to bleed off air.
  • No-load running time cannot exceed 5 seconds. The pump must run with liquid; otherwise the mechanical seal may be damaged.

Startup and operation:

  • Start the prime mover and gradually open the gate valve to the required position.
  • Stop the machine if noise or other abnormal phenomena occur.

Lubrication and Maintenance

  • Bearings shall be lubricated with universal lithium-based grease.
  • Replace the grease every 1500 hours of operation.
  • During disassembly, remove the pump body, impeller nut and stop washer, then remove the impeller.
  • Remove the mechanical seal pump cover and mechanical seal; remove the bearing glands.
  • Use a copper stick or wood block to remove the shaft and bearing components without damaging the shaft shoulder.

Inspection:

  • Impeller: replace if serious cavitation, excessive corrosion, ablation or breakage.
  • Shaft: repair or replace when radial runout exceeds 0.05 mm, oil seal location is seriously abraded, or shaft thread/groove/pedestal is damaged.
  • Oil seal: disassembled oil seals must be replaced.
  • Bearing: replace if excessively worn, too tight/loose, or noisy.

Troubleshooting

FaultCauseTroubleshooting
Excessive shaft powerImpeller friction; lift much lower than design pointAdjust clearance; check service machine; reduce drainage valve opening
Reduced lift and flowBlocked suction pipe/impeller; lower speed; worn impeller; excessive clearance; inlet valve too smallRemove blockage; run at rated speed; replace impeller; adjust clearance; open inlet valve
Bearing overheatToo much/little lubricant; foreign substances; worn bearingKeep oil level; replace lubricant; replace bearing
Vibration and noiseUnbalanced impeller; worn bearing; loose connection; cavitationReplace impeller; replace bearing; tighten parts; improve suction condition
Sealing leakageWorn shaft sleeve; foreign substances; seal skew; worn sealReplace shaft sleeve; clean; reinstall; replace mechanical seal

Data source: Series Sand Pump (Spraying pump) Installation and Operation Instructions.