The ZQ127/25Y TEDA drill pipe power tong installation involves three key steps. Lift the tong with the lifting bucket connected to the master tong lifting bar, positioning the lifting point 15m above the wellhead with the tong head center 0.5m from the well center in free suspension. Level the tong by adjusting the screws on the lifting bar to ensure proper clamping. Tie the back guy to the rig and the back guide pole seat, rated at 50KN load, keeping it vertical to the pipe during make-up for operator safety.

Conatct For Details
DetailReview(0)Additional

Proper installation of the ZQ127/25Y TEDA Drill Pipe Power Tong is essential for safe, efficient make‑up and break‑out of drill pipe, tubing, and casing in well workover operations. Follow these three installation steps carefully to ensure correct positioning, leveling, and safety line rigging.

3.1 Lifting

Connect the lifting bucket to the lifting bar of the master tong and lift the drill pipe tong at the well servicing rig. The lifting point should be positioned 15 meters above the wellhead. In the state of free suspension, the center of the tong head should be 0.5 meters away from the wellhead. The suspension height is appropriate when the backup tong can clamp the drill pipe connector or the coupling of tubing or casing. This ensures proper positioning for reliable clamping during make‑up and break‑out operations.

3.2 Leveling

Adjust the adjusting screws on the lifting bar to keep the drill pipe tong level. Proper leveling is critical – if the tong is not level, the clamping will fail to work, resulting in improper gripping and potential damage to the pipe or tong components. Use a spirit level to verify horizontal alignment in both directions before commencing operations.

3.3 Tie the Back Guy

The back guy is a critical safety component that prevents the tong from rotating unexpectedly during clamping operations. Tie one end of the back guy to the rig and the other end to the seat of the back guide pole of the drill pipe tong. The back guy must be capable of bearing a load of 50 KN. When the drill pipe is in the making‑up state, the back guy should be vertical (perpendicular) to the drill pipe to ensure operator safety. This perpendicular orientation ensures that reactive torque is transmitted directly into the rig structure without inducing lateral loads on the tong.

Installation Checklist

The following steps should be completed during installation:

  • Connect lifting bucket to master tong lifting bar

  • Position lifting point 15m above wellhead

  • Set tong head center 0.5m from well center in free suspension

  • Verify suspension height allows backup tong to clamp pipe connector or coupling

  • Adjust leveling screws on lifting bar

  • Verify tong is horizontal with spirit level

  • Tie back guy to rig and back guide pole seat

  • Verify back guy can bear 50KN load

  • Ensure back guy is vertical to pipe during make-up

Safety Notes

  • Always use properly rated lifting equipment for hanging the tong.

  • Ensure the lifting point is securely positioned above the wellhead.

  • Never operate the tong before completing all installation steps.

  • Verify the back guy is securely anchored to a structurally sound point.

  • The back guy must bear a minimum load of 50 KN.

  • Always ensure the back guy is vertical to the pipe during make‑up operations.

  • Regularly inspect the back guy for wear or damage.

For installation support, custom rig adaptations, or to request detailed installation diagrams, please contact us via email at info@hyrig.com.