On a BPM DQ50BSC top drive, the 9703340000 Upper IBOP is the primary mechanical barrier inside the drill string. Together with the lower IBOP (if installed) and the BOP stack, it forms a complete pressure containment system.
The BPM top drive series, including the DQ50BSC, has been widely adopted in domestic and international drilling operations. Its design and parameters are similar to international top drives such as Varco TDS series.
Whenever the top drive disconnects from the drill pipe, the upper IBOP must be closed. This prevents:
Mud spilling onto the rig floor
Backflow from the drill string if the float valve fails
Loss of hydrostatic head inside the drill pipe
Procedure: Stop circulating → Close upper IBOP → Observe pressure → Break connection.
When pulling pipe out of the hole:
| Float valve present? | Upper IBOP position |
|---|---|
| Yes (operational) | Closed as backup only |
| No (float not used) | Must be closed at all times while tripping |
| Float valve failed | Close upper IBOP immediately |
When the well flows (positive kick indication), the driller must:
Stop rotation and pump.
Close the upper IBOP immediately.
Close the lower IBOP (if installed).
Close annular BOP.
Record shut-in drill pipe pressure (SIDPP) and shut-in casing pressure (SICP).
Prepare for well kill operation.
When using the DQ50BSC top drive to circulate out a kick:
Circulating: Upper IBOP open (drilling mud flows through it)
Not circulating (pressure check, etc.): Upper IBOP closed
| Event | Action |
|---|---|
| Normal drilling | IBOP open |
| Kick detected | Stop pump → Close upper IBOP → Close BOPs |
| After BOPs closed | Record pressures |
| Prepare to circulate | Confirm IBOP closed, open lower IBOP slowly |
| Begin kill circulation | Open upper IBOP slowly, start pump |
| Pause circulation | Stop pump → Close upper IBOP |
| Kill complete, well static | Pressure test IBOP before opening |
| Barrier | Purpose |
|---|---|
| Upper IBOP 9703340000 | Stops flow inside drill pipe above top drive |
| Lower IBOP | Stops flow inside drill pipe below top drive |
| Annular BOP | Seals around the drill pipe in annulus |
| Ram BOPs | Shear or seal around pipe / close open hole |
Test the upper IBOP every 14 days or before each new well section per API 16D.
Cycle the valve every shift – ensures it will move when needed.
Post a visible procedure at the driller’s console.
Train all drill crews – simulate closing IBOP in well control drills.
Keep a spare upper IBOP on location for immediate change-out.
Closing IBOP before stopping pump – pressure surge may damage seals.
Forgetting to close IBOP before breaking connection – mud spill and possible well flow.
Using IBOP as a choke – never partially open under pressure; fully open or fully closed only.
Neglecting low-pressure test – small leaks may go undetected.
Attempt to close it using a cheater bar (controlled force).
If still open, use the lower IBOP if installed.
If no lower IBOP, strip back to BOPs and close annular.
Pump barite plug if necessary.
Equalize pressure across the valve (if possible).
Use a second T-handle or extension bar.
If still stuck, replace the IBOP at the next connection.
We provide:
Well control worksheets for IBOP integration with BPM DQ50BSC
Quick-reference card for driller’s console
API 16D test report templates
For training materials, emergency support, or spare IBOPs: info@hyrig.com
Also available: Lower IBOP and other BPM DQ50BSC top drive spare parts.
total 0 Sheet,Only 5 images can be uploaded, each less than 5m.