The Regenerator Bottom Pump is designed to remove the stripped liquid from the bottom of a regenerator (stripper) column in gas sweetening, refinery hydrodesulfurization (HDS), carbon capture (CCUS), and other amine or solvent regeneration processes. The most common fluid handled is lean amine – the regenerated amine solution that has been stripped of H₂S and CO₂ – which is then sent to a reboiler for steam generation or directly to the lean amine charge pump for circulation back to the absorber. The pump may also handle other regenerator bottoms such as stripped sour water, glycol, or solvent.
Because the fluid is typically hot (100–130°C), may contain residual H₂S, and is corrosive, the pump must meet the highest standards of reliability, thermal stability, and leakage containment. All pumps are fully compliant with API 610 11th/12th edition (ISO 13709) – ensuring a 20‑year design life and minimum 3‑year uninterrupted operation.
| Pump Type | Configuration | Best Regenerator Bottom Application |
|---|---|---|
| OH2 (Preferred) | Overhung, centreline‑mounted, single‑stage | Lean amine transfer to reboiler or lean charge pump (heads ≤150 m, flows 10–600 m³/h) |
| BB3 | Axially split, multistage, between bearings | High‑head transfer (heads >150 m) to distant equipment or high‑pressure systems |
| VS4 | Vertical suspended sump / can type | Sump evacuation, low NPSHa, or space‑constrained installations |
| Parameter | OH2 | BB3 | VS4 |
|---|---|---|---|
| Flow range | 10 – 600 m³/h | 50 – 1500 m³/h | 10 – 750 m³/h |
| Head range | 20 – 260 m (typical 50–150 m) | 100 – 1500 m | 15 – 280 m |
| Pressure rating | Up to 64 bar | Up to 150 bar | Up to 40 bar |
| Temperature | –45 to +200°C | –45 to +200°C | –46 to +260°C |
| Speed | 1,450 / 2,950 rpm | 1,450 / 2,950 rpm | 1,450 / 2,950 rpm |
Lean amine at regenerator bottom is typically 110–130°C and may contain residual H₂S and heat‑stable salts. 316L stainless steel (API 610 Class S‑8) is the minimum standard. Carbon steel corrodes rapidly at these temperatures.
| Component | Material (Standard) | Upgrade Option |
|---|---|---|
| Casing | 316L SS (CF3M) | Duplex (D‑1/D‑2), Super Duplex (U‑8) |
| Impeller | 316L SS | Duplex, Super Duplex, 17‑4 PH |
| Shaft | 316 SS or 4140 with coating | 17‑4 PH, Duplex SS |
| Wear rings | 316L SS + Stellite hard‑facing | Tungsten carbide |
| Gaskets / O‑rings | Spiral wound (graphite) / FKM | Aflas for higher temperature |
For lean amine with H₂S residual above NACE limits, NACE MR0175 / ISO 15156 certification is required.
Although lean amine has less H₂S than rich amine, residual H₂S and high temperature still require robust sealing. Dual pressurized seals (API 682 Arrangement 3) with Plan 53B are recommended. For clean, low‑H₂S lean amine, a tandem seal with Plan 52 may be acceptable.
| Seal Arrangement | API 682 Plan | Application |
|---|---|---|
| Dual pressurised (Arr. 3) | Plan 53B | Recommended – zero emissions, handles hot lean amine safely |
| Tandem seal (Arr. 2) | Plan 52 | Acceptable for very low H₂S, well‑ventilated areas |
| Single seal (Arr. 1) | Plan 11 / 23 | Not recommended for hot amine; Plan 23 (cooled) may be used for water‑like fluids |
Plan 53B provides barrier fluid pressurised above process pressure. Seal faces: silicon carbide (SiC) / SiC. Elastomers: FKM for up to 120°C; Aflas for higher temperatures.
The regenerator bottom pump typically takes suction from the bottom of a column operating near atmospheric pressure (or slight vacuum in some designs). NPSHa is often limited to 3–6 meters from the liquid level above the pump centreline. The fluid is hot, near its boiling point. Dissolved gases (CO₂, H₂S, methane) can flash easily.
Ensure suction piping is short, direct, and insulated.
Calculate NPSHa at the bubble point – do not assume subcooling.
Select a low‑NPSHr impeller or add an inducer if margin is insufficient.
Maintain NPSHa ≥ NPSHr + 1.0 m per API 610.
During normal operation, the regenerator bottom pump continuously circulates lean amine to the reboiler or to the lean charge pump. If the downstream valve closes, an automatic recirculation valve (ARC) or a continuous bypass with orifice must return minimum flow to the regenerator bottom.
| Industry | Process | Fluid | Recommended Configuration |
|---|---|---|---|
| Natural gas sweetening | Amine regeneration | Lean MDEA / MEA (110–130°C) | OH2 (standard) |
| Refinery HDS | Amine stripping | Lean MDEA / DEA | OH2 or BB3 |
| CCUS (carbon capture) | MEA regeneration | Lean MEA | OH2 |
| Sour water stripping | Sour water regenerator | Stripped sour water | OH2 (316L SS or duplex) |
| Glycol dehydration | Glycol regenerator | Lean glycol | OH2 (carbon steel or 316L) |
Design life: 20 years minimum
Continuous operation: Minimum 3 years uninterrupted service
Bearing life: L10 ≥25,000 hours
Critical speed: ≥120% of maximum operating speed
Centreline mounting (OH2/BB3): Essential for hot service (100–130°C)
Hydrostatic test: 1.5x design pressure
Performance test: Water per API 610 Grade 1 or 2
Material certification: EN 10204 3.1 full traceability
NACE MR0175 / ISO 15156 available for sour lean amine
Full API 610 compliance (OH2 / BB3 / VS4) – 11th/12th edition ISO 13709, 20‑year life
316L stainless steel (S‑8) as standard – proven corrosion resistance in hot lean amine
API 682 Plan 53B dual pressurised seals – zero emissions, safe hot amine handling
Broad hydraulic coverage – flows 10–1500 m³/h, heads 20–1500 m
Low NPSH designs – inducer option for low‑elevation regenerator columns
Centreline mounting – maintains alignment during thermal cycling (up to 200°C)
Easy maintenance – back pull‑out (OH2), axial split (BB3), vertical withdrawable (VS4)
Minimum flow protection – ARC or bypass integrated
NACE MR0175 / ISO 15156 compliant options
Field proven – thousands of regenerator bottom pumps in gas plants and refineries worldwide
| Component | Recommended Quantity |
|---|---|
| Mechanical seal cartridge (Plan 53B ready) | 1 set |
| Bearing set (radial + thrust) | 1 set |
| Wear ring set (casing + impeller) | 1 set |
| Gasket / O‑ring kit (full set) | 1 set |
| Inducer (if fitted) | 1 set |
For selection of the correct Regenerator Bottom Pump for your amine or solvent regeneration unit – including column bottom conditions (temperature, pressure, fluid composition), NPSHa calculation, material selection (316L SS, duplex, or NACE MR0175), API 682 seal plan (Plan 53B), and complete API 610 data sheet – please contact our engineering team.