HYRIG can supply the XBSY WJQ5×6J shear pump range and spare parts. This guide summarizes the installation, operation and maintenance requirements from the manual.

Installation

  • Locate the pump near the liquid source so the suction line can be short and losses reduced.
  • The foundation should be sufficiently rigid and substantial to absorb vibration and support the base plate at all points.
  • The base plate should be installed in a level position.
  • For pulley installation, the axes of two pulleys must be parallel and the end surface error cannot exceed 2 mm; belts should be aligned and tightened; the electric motor must be mounted stably.
  • The suction line should be equal to or larger than the pump suction.
  • The suction line should not be throttled; a positive shut-off valve may be installed for pump removal and maintenance.
  • The suction line should eliminate air pockets and slope gradually downward to the supply source.
  • The suction line should have a straight section into the pump of at least two times its diameter.
  • For temporary flexible hose, use a non-collapsing hose.
  • A positive shut-off valve should be located in the discharge pipe.
  • All pipes should be independently supported and accurately aligned; the pump must not support pipe weight.
  • If operating conditions are not known accurately, provide a throttle valve in the discharge line.
  • If connected to a pressurized system, install a check valve between the discharge and throttling valve to prevent back flow.

Operation

Preparation:

  • Pump rotates freely by hand.
  • Check the pump rotation direction; the correct direction is shown by an arrow on the casing.
  • Open the suction valve fully.
  • Fill the pump and suction line with fluid to vent air.

Running:

  • Start the motor after completing all preparations.

Lubrication:

  • Add a good grade of 30# weight motor oil until the middle level of the dipstick. Do not overfill.
  • Oil should be changed every 90 days or 1000 hours.
  • Under special conditions, a grease that can dissolve with the motor oil may be selected for lubrication.

Maintenance and Inspection

  • The pump employs mechanical seal as its primary seal and packing seal as its secondary seal. Packing seal can be compacted only when the mechanical seal is disabled; otherwise the seal may be damaged.
  • No-load running time cannot exceed 5 seconds. The pump must run filled with liquid slurry; otherwise the mechanical seal may be damaged.
  • Impeller: replace if excessive erosion, corrosion, extreme wear, or vane breakage.
  • Shaft: replace if run-out exceeds 0.05 mm; bearing seats and oil seal area must be smooth and free of scratches or grooves.
  • Shaft sleeve: replace if grooved.
  • Oil seal: removed oil seal must be replaced.
  • Ball bearings: replace if worn, loose, or rough and noisy when rotated.
  • O-rings and gaskets: recommended to remove and replace during disassembly; reuse only if not worn or damaged.
  • During assembly, the clearance between the back of the impeller and the protecting plate is 0.6 mm.
  • Packing gland should be tightened finger tight only; over-tightening may burn the packing when the pump is started.

Troubleshooting

FaultCauseTroubleshooting
Excessive shaft powerImpeller friction; pump works below designed head; packing over-tightened; belt slipsAdjust clearances; check complete machine; readjust gland; re-tighten belts
Fall in head and capacityBlocked suction/impeller; speed drop; worn impeller; excessive clearance; inlet valve too smallRemove blockage; run at rated speed; replace impeller; adjust impeller; increase opening
Bearing overheatToo much/little lubricant; impurities in lubricant; worn bearingKeep oil level; change lubricant; replace bearing
Vibration and noiseUnbalanced impeller; worn bearing; loose connection; cavitationReplace impeller; replace bearing; tighten parts; improve suction condition
Excessive leakage when stoppingOver-worn seal; extremely worn shaft sleeve; extremely worn packingRenew seal; replace sleeve; renew packing

Data source: Shear Pump Directions For Installation And Operation, Table 3.

Contact