The KHT9625 casing power tong requires proper installation and standard operation for safe and efficient performance. Installation steps include hanging with 3-ton pulley and ≥1/2″ wire rope at casing joint level, leveling via front/rear and crosswise screws to prevent gear slip, securing back guy with ≥5/8″ wire rope at 90° to tong centerline, cylinder oil fill using hand pump when piston rod < 1/4″, and pipe connection (high pressure NPT1, low pressure return NPT1 1/4″). Standard make-up: backup tong clamps pipe → master tong clamps casing → high gear for spinning → lower gears for torque → release tongs → open safety door. Break-out: low gear to loosen → high gear for fast unthreading → release and remove. Critical rules: no gear shifting during operation, safety door must be closed, align tong center with casing center. Contact info@hyrig.com.

Conatct For Details
DetailReview(0)Additional

This guide provides step-by-step instructions for the proper installation and standard operation of the KHT9625 Casing Power Tong. Following these procedures ensures safe, efficient, and reliable performance during casing make-up and break-out operations.


Installation Steps

Proper installation is critical for safe operation and equipment longevity. Follow these steps carefully:

StepProcedureKey Requirements
1. HangingUse a 3-ton pulley and ≥1/2″ wire rope. Set the hanging height to align with the casing joint level.Ensure pulley and rope are rated for the load.
2. LevelingAdjust front/rear and crosswise leveling screws to ensure the tong is perfectly horizontal.Prevents gear slippage and uneven wear.
3. Back GuySecure a back guy line using ≥5/8″ wire rope at a 90° angle to the tong centerline.Provides stability during high-torque operations.
4. Cylinder Oil FillUse a hand pump to fill cylinder oil when the piston rod extends less than 1/4″.Maintains proper hydraulic cylinder function.
5. Pipe ConnectionConnect hydraulic lines: High pressure port: NPT1; Low pressure return port: NPT1 1/4″.Ensure tight, leak-free connections.

Standard Make-Up Procedure (Tightening)

Follow these steps for proper casing make-up:

  1. Backup tong clamps pipe – Engage the backup tong to secure the lower pipe section.

  2. Master tong clamps casing – Engage the master tong to grip the upper casing.

  3. Use high gear for spinning – Run at high speed for fast thread engagement.

  4. Switch to lower gears for torque – Shift down as needed to achieve target torque.

  5. Reach target torque – Monitor torque gauge; stop when specified torque is reached.

  6. Release master & backup tong – Disengage both tongs.

  7. Open safety door – Unlock and open the safety door.

  8. Remove tong – Lift and move the tong away from the wellhead.


Standard Break-Out Procedure (Loosening)

Follow these steps for proper casing break-out:

  1. Use low gear to loosen connection – Engage low gear for high torque to break the thread connection.

  2. Switch to high gear for fast unthreading – Once loosened, shift to high gear for rapid spinning.

  3. Release tongs – Disengage both master and backup tongs.

  4. Remove tong from wellhead – Lift and clear the tong.


Critical Safety Rules

Adhere to these critical rules at all times to prevent accidents and equipment damage:

  • No gear shifting during operation – Always stop the rotation before changing gears. Shifting under load can damage the transmission.

  • Safety door must be closed during working – Never operate the tong with the safety door open. The door interlock prevents operation when open.

  • Align tong center with casing center – Misalignment can cause uneven gripping, thread damage, or tong component failure.


Additional Safety & Operational Tips

  • Pre-start check – Verify all connections, hydraulic pressure, and safety devices before each operation.

  • Proper jaw selection – Use the correct jaw size for the casing being handled (see jaw size chart).

  • Regular maintenance – Inspect wire ropes, pulleys, and hydraulic hoses for wear before each shift.

  • Emergency stop – Know the location of emergency shutdown controls.


Troubleshooting Common Installation Issues

ProblemPossible CauseSolution
Gear slippingTong not levelRe-level using adjustment screws
Excessive vibrationBack guy not at 90° angleReposition back guy wire rope
Slow cylinder responseLow oil level in cylinderUse hand pump to refill cylinder oil
Hydraulic leakLoose pipe connectionsTighten NPT fittings

Contact Us for Support

For installation assistance, operator training, or replacement parts, please contact us:

info@hyrig.com

We provide full technical support for all TEDA casing power tongs, including the KHT9625.