On a VARCO TDS-4SA top drive, the Lower IBOP 114706-500 provides redundant isolation inside the drill string. While the upper IBOP (110103-500) is the primary barrier, the lower IBOP is the secondary barrier. API 16D recommends dual IBOPs for critical wells.
| Scenario | Upper IBOP | Lower IBOP |
|---|---|---|
| Normal drilling | Open | Open |
| Before breaking connection | Closed | Open (or closed) |
| Upper IBOP leaks when closed | Leaking | Closed – contains pressure |
| Upper IBOP fails to close | Failed open | Closed – provides isolation |
| Need to service upper IBOP | Removed | Closed – allows safe removal |
Upon detecting a kick, the driller closes both upper and lower IBOPs. This ensures that even if the upper IBOP has minor leakage, the lower IBOP holds pressure.
Procedure: Stop pump → Close upper IBOP → Close lower IBOP → Close BOPs.
If pressure testing shows a slow drop when upper IBOP alone is closed, close the lower IBOP to confirm isolation. If pressure stabilizes, the upper IBOP requires maintenance.
The lower IBOP can be closed and pressure bled off between the two valves. This creates a trapped pressure zone, allowing the upper IBOP to be removed and serviced while the drill string remains under pressure below.
When tripping pipe out of the hole and no float valve is present, both IBOPs should be closed at all times for absolute isolation.
Before opening the upper IBOP when there is pressure trapped below, use the lower IBOP to equalize:
Close upper IBOP.
Close lower IBOP (trap pressure between them).
Open a small bleed valve (if available) or crack the connection slowly.
Once pressure equalizes, open upper IBOP.
Note: The 114706-500 does not have a built-in equalization port. Equalization is done via a separate bleed valve or by gradually cracking the connection above the lower IBOP.
| Step | Action |
|---|---|
| 1 | Close lower IBOP (114706-500). |
| 2 | Bleed pressure from the space between upper and lower IBOP via top drive washpipe or bleed valve. |
| 3 | Verify zero pressure. |
| 4 | Remove upper IBOP. |
| 5 | Lower IBOP holds well pressure below. |
If upper IBOP fails (cannot close or leaks severely), the lower IBOP becomes the primary barrier. In this mode:
Do not open lower IBOP unless necessary.
Plan to replace upper IBOP at the next connection.
If both IBOPs fail, rely on BOP stack and consider stripping.
| Barrier | Purpose |
|---|---|
| Upper IBOP (110103-500) | Primary internal barrier |
| Lower IBOP (114706-500) | Secondary internal backup |
| Annular BOP | Seals around drill pipe in annulus |
| Ram BOPs | Shear or pipe rams |
Test both IBOPs separately – lower IBOP test with upper IBOP open, then both closed.
Cycle both valves daily – ensure each can move freely.
Mark positions clearly – use visual indicators for open/closed.
Drill crew training – practice dual IBOP failure scenarios.
Upper IBOP is still available as primary barrier.
Strip back to BOPs and close annular/rams.
Replace lower IBOP at the next trip.
Immediately close annular BOP.
If possible, close pipe rams.
Consider shear rams if well continues to flow.
Pump barite plug.
❌ Using lower IBOP as the primary barrier for routine connections (use upper IBOP first).
❌ Opening lower IBOP before verifying no pressure below.
❌ Forgetting to close lower IBOP before removing upper IBOP.
❌ Relying on lower IBOP as a choke – never partially open.
We provide:
Dual IBOP well control worksheets
Quick-reference cards for driller’s console
API 16D test report templates
For training materials, emergency support, or spare lower IBOPs:
Email: info@hyrig.com
*Also available: Upper IBOP 110103-500 to complete dual barrier isolation.*